3

Establishing Mortuary Cooler Perimeter

A. The following instructions cover the erection of Mortuary Coolers that do not include Bally floor panels and

are shipped unassembled.

B. Mark the outside perimeter of the Mortuary Cooler on the building floor. Check the marked area for

squareness by measuring the distance across the corners as shown in Figure 4. Check floor for levelness. If

floor is not level, the panels will need to be shimmed to maintain the height of the highest point of floor.
Determine the highest point of floor using o 48" spirit level. If needed, establish a level string to help set

vertical panels. See Figure 5.

Vertical Panel Assembly

A. Position the first corner panel (#1) so the

outside of the panel is flush with the
perimeter line. If necessary, shim corner panel

to be level with the highest point of floor.


B. Position the center back vertical panel (#2) to

the corner panel and lock the adjoining side
Speed-Loks. Shim the second panel if

necessary for it to be plumb and level with
the corner panel. Ensure that the tops of the
panels are even. Insert Speed-Lok wrench

into access hole and turn clockwise until the
Speed-Lok locking arm stops. If Speed-Lok
was fully open, the wrench should make one

complete turn. See Figure 6 and 7.

C. Position the next rear corner panel and lock to

previously installed vertical panel. Check
panels for plumbness and levelness.


D. Proceed to position and lock the side vertical

panels as numbered. Check each vertical
panel for plumb and level when installed.