Installing Door Panel

A. Remove the steel-shipping strap mounted at

the bottom of door panel opening. Position

door panel and align with vertical panels

previously installed.


B. Door panel is considerably heavier than vertical

panels and needs to be handled by at least (2)

able-bodied personnel. Ensure that door
panel is plumb and level and lock the

adjoining Speed-Loks. Shim door panel if
needed. If door panel is not installed plumb

and level, the door will not operate properly.


Installing Ceiling Panels


A. The Mortuary Cooler ceiling is made up of (2) ceiling panels that are locked together at the factory. Unlocking the

ceiling panels will damage the refrigeration unit opening.


B. Place ceiling panels on top of Mortuary as shown on the plan view. Align the edges with the vertical panels and

lock top Speed-Loks.

Anchoring Mortuary Cooler

A. Vertical panels are mounted to the building

floor using continuous angle, concrete anchors
and self-drilling metal (TEK) screws.

B. Angles are shipped in stock lengths and must

be cut before installation. Calculate angle

length by measuring inside of wall panels and
subtract 4 ". Angles will start 2" from each end
wall. See Figure 8.


C. Set angle along bottom of vertical panels with

larger holes on floor and mark concrete anchor

holes with a builders crayon or similar method.

D. Drill ¼” hole 2" deep in concrete at marked

locations. Set angles back in place and install
concrete anchors. Install self-drilling metal

screws (TEK) through upright leg of angle
through predrilled holes.