Electrical Planning

Power Requirements

Each barrier gate requires a 115-120 VAC on a 5-Amp dedicated breaker, which should be provided
during wash construction. Most installers will have power supplied directly from one of the three phases
used to power the wash motors and controllers. If this method is used, special attention should be
given to proper grounding at the unit, as well as in the breaker panel.

Note: Follow all local and national electrical codes!

Conduit Requirements

Plan your conduit runs so that the barrier gate control signal wiring and the loop wiring enter through
the bottom of the base of the gate. Figure 1 shows a typical site layout with the following conduit runs:

• A conduit between the AC service panel and the entry units for power wiring.
• A conduit between the entry units and gates for power wiring.
• A conduit between the gate controller (located in the equipment room) and the entry units

for control signal wiring.

• A conduit between the entry units and the gates for control signal wiring.
• Conduit between the gates and loops the loop leads.

Wiring Requirements

Wires to be pulled through the conduits are listed in the following tables. Wires should be 18
AWG (minimum) and color-coded to facilitate installation and troubleshooting. The quantities
shown are per lane.

Qty

From

To

Function

3

AC Service Panel

Gate

Gate Power (115 VAC)

4

Gate Controller

Entry Units

Control wires

3

Gate Controller

Gate

Control wires

Loop Planning and Installation

General

Unitec provides 18-foot vehicle detection loops that can be used for the gate arm reset or merge
loops. Two loop types are available: direct burial and saw cut installation. Direct burial loops