Series 8700 / 8800 Unitized Curtain Wall Assembly Instructions - Volume 5

Section 25 - Captured Vent Unit Glazing at Stack Sill : A. Temporary Glazing Locators

Figure 75

1. Apply two temporary glazing locators (KV03) with isolators and setting blocks at approximate quarter points at the horizontal at the head of the vent opening

and intermediate horizontal locations.

2. Refer to Volume 2, page 20 and 21 of the S-8000 Unitized Curtain Wall Assembly Instructions for assembly details and notes.

Temporary Glazing

Locators

HEAD

SILL

Concealed Vent

opening

Intermediate

Horizontal

Concealed Vent

Stack Sill

Concealed Vent Head

Intermediate Horizontal

Concealed Vent

Head

Temporary Glazing

Locators (KV03)

KV03

KV03