0 installation, 1 weighbridge installation, Installation – Rice Lake SURVIVOR RT Rail Scale User Manual

Page 7

Advertising
background image

Installation

3

2.0

Installation

This section describes the assembly procedure for the

Survivor

®

RT

railroad track scale.

Crush hazard, keep hands, feet and other body parts clear when setting weighbridge modules in place.
Moving parts can crush and cut.

2.1

Weighbridge Installation

1. Set load cell lower base plates in place on

embedded anchors and place necessary

components for each cell at cell location. Refer

to assembly print.

Figure 2-1. Load cell lower base plate

2. Assemble base plates, load cells, and hardware

on lower base plate and set to approximate

height at each location.

Figure 2-2. Base plates, load cells, and hardware installed

on lower base plate

3. Set longitudinal checking brackets in place on

embedded hardware as indicated on print.

Figure 2-3. Longitudinal checking bracket

4. Set module on wooden blocking in foundation.

(Place lateral check rods through modules

prior to placing in foundation.)

Figure 2-4. Module on wooden blocking

5. Install side checking rods in weigh bridge prior

to placing the modules.

Figure 2-5. Checking rods installation

6. One section at a time, starting with an end, jack

the modules in place and attach shim plate,

bearing cushions, mount top plate, load cell

bearing plate, splice plates, and hardware.