1 corrugated metal sheeting, Corrugated metal sheeting – Rice Lake SURVIVOR PT Series User Manual
Page 14
10
Survivor PT - Pit Type Truck Scale
Grouting
1. Erect temporary dams around each baseplate and inject 9000 psi non-shrinking, epoxy/cement grout.
2. Take care not to leave air voids; the baseplate must have even support from continuous grout contact.
After the grout has hardened, tighten anchor bolt nuts until the heads expand and the bolts are solidly
anchored.
Figure 3-7. Grout example.
3.5
Install Support Bars, Corrugated Metal, and Deck Rebar
3.5.1
Corrugated Metal Sheeting
To support the concrete deck pour, 26-gauge galvanized corrugated metal sheeting (15/16" by 3 3/4" wide
corrugations) is installed on the main frame assembly. The panels are installed perpendicular to the cross beams
and rest on the cantilever support channels, the main beams, and the frame cross beams.
1. Install the sheet metal starting below the Nelson studs along one side of the frame.
2. Form the sheet metal to the contour of the frame assembly and overlap adjoining panels a minimum of 15"
or four full corrugations.
Figure 3-8. Installation of Support Bars, Corrugated Metal, and Deck Rebar.
Panels must fit closely to the vertical webs of all support beams to prevent concrete run-out during the
deck pour.
Note
CHANNEL
NELSON STUD
CANTILEVER
SUPPORT
MAIN BEAM
CROSS BEAM
CORRUGATED METAL
MINIMUM OVERLAP
DRAWING NOT TO SCALE)