Assemble Deck Modules

5

15. If required, place and install any additional center modules in a similar manner.

16. Install the remaining end module on four setting blocks ensuring the end beams are aligned with and in

direct surface contact with the center module.

Figure 2-3. Module Installation

17. Center the module side-to-side and check that the end of the main beam is 3/4" from the end of the

concrete pit wall. Install and tighten the three top bolts on each beam (inside and outside) finger tight as in
the previous operation.

Do not install the bottom bolt at this time.

18. To reduce the on-site crane operating time, the manhole frame (shown in Figure 2-4 on page 5) can be

installed at this time. It is recommended to locate the frame in a central location close to the J box as shown
in Figure 2-5 on page 5.

Figure 2-4. Manhole Frame

Before installing the manhole frame, remove a section of the corrugation support bar in the location where the
manhole frame is to be installed. Additional manholes are available as options. Consult with local weights and
measures officials for any state restrictions or access in the state being installed.

OSHA may have restrictions on pit access. Consult with customer’s safety engineers for details.

Figure 2-5. Optimal Manhole Frame Location

Note

Manhole Frame

(24" square)

Note

Top View

To Scale House

Suggested Location of Manhole

Junction Box

Corrugation Support Bar

(remove material as needed

to install manhole frame)