Initial Start Up

19

Before operating the ironer, check the
following:

1. Check that the machine is level and

in a stable position on the floor. The

machine should not rock or move in any
way.

2. Ensure that all electrical, gas/steam,

and exhaust connections are made and

leak free.

3. Check that the ironer is correctly

grounded according to the earlier listed

specifications (see page 8).

4. Remove all packaging and protective

shipping materials. Discard these items -

do not store them near the ironer.

5. Inspect the thermostat sled assembly

and make sure it is in full contact with

the ironing cylinder, and is free of lint

and debris.

6. Turn the heating control to the OFF

position, and the speed control to

minimum (fully counter-clockwise).

7. Apply power to the machine. Before
doing this, double check that the supply

voltage matches the information on the

serial sticker of the ironer.

8. Press the green START button.

9. Double check that the exhaust fan is
rotating in the direction indicated on the

blower housing. Additional information

can be found on page 17.

10. Make sure the feeding belts are
acting to pull linen into the machine

(belts traveling towards the heated

cylinder)

11. Replace all panels.

12. For gas units, move the heat switch

to the ON position. The heat light turns

on. There will be a delay of 30 seconds
prior to ignition.

13. Check that the temperature

increases. When the temperature

reaches the set point, the heat light
should turn off.

14. Use old or worn linen to perform

the initial ironing test.

15. Lay the linen on the feeding belts

and allow it to be pulled into the ironer.

16. Adjust the speed control so that the

goods come out of the ironer dry and
finely pressed.