Cycle Segment Charts (continued)

Programming

Details

Use Up or Down to change. Start key is enter or advance

00 or 02 - 30

Segment time: 00 to skip, or any time between 0 and 30 minutes

HFIL CFIL BFIL

Fill temperature: Hot, Cold, or Warm (both fill)

LOLE or HILE

Select Fill level, Low or High

SUP0 - SUP7

Select Supply 0-7 (0 for no supply during the step)

00, 75 - 200

00, 25 - 93

SPIN flases for 1 sec
TIME flases for 1 sec
00 or 30 - 120

Select time for spin: 30 - 120 seconds. 00 for no spin.

Note: Supply 4 and 7 are only availble if enabled in Setup
Note: Heat is only available if enabled in Setup

Display

UASH

Enter temperature: 75-200 deg F, 25-93 deg C. 00 for no heat.

Select 00 if you have programmed a Flushing Prewash

Wash Segment

Details

Use Up or Down to change. Start key is enter or advance

drin or srin

(1) Select Rinse Method: Dilution Rinse or Spray Rinse

00 or 02 - 30

(2) Segment time: 00 to skip, or any time between 0 and 30 min

HFIL CFIL BFIL

(3) Fill temperature: Hot, Cold, or Warm (both fill)

LOLE or HILE

(4) Select Fill level, Low or High

SUP0 - SUP7

(5) Select Supply 0-7 (0 for no supply during the step)

00, 75 - 200

00, 25 - 93

SPIN flases for 1 sec
TIME flases for 1 sec
00 or 30 - 120

(7) Select time for spin: 30 - 120 seconds. 00 for no spin.

Note: Heat is only available if enabled in Setup
Note: If Spray Rinse is selected for the segment, steps 3 to 6 are skipped.

fil1 fil2 fil3 fil4 fil5

(6) Enter temperature: 75-200 deg F, 25-93 deg C. 00 for no heat.
Select 00 if you have programmed a Flushing Prewash

Note: Supply 4 and 7 are only availble if enabled in Setup