14

D
GB
F
E

09702-09.2013-DGbF

5| Compressor assembly

5.6 Operating the shut-off valves

5.5 Laying suction and discharge lines

INFO!

Proper layout of the suction and discharge lines directly after

the compressor is integral to the system’s smooth running and

vibration behaviour.

ATTENTION! Improperly installed pipes can cause cracks and tears, the result

being a loss of refrigerant.

A rule of thumb:
Always lay the first pipe section starting from the shut-off valve

downwards

and parallel to the drive shaft.

Fig. 18

Rigid
Fixed point

As short as
possible

Valve spindle seal

Before opening or closing the shut-off valve, release the valve spindle seal by approx. ¼ of a turn

counter-clockwise.

After activating the shut-off valve, re-tighten the adjustable valve spindle seal clockwise.

Fig. 19

Fig. 20

loosen

tighten