CHAPTER 3 – INSTALLATION

OMM-0100_0B

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

Page 33 of 156

GF-146

Ph.: 800-526-0288

PRI - 07/14/14

Unpacking Instructions (Cont.)

4. Install the two factory supplied eyebolts “D” on the upper side of the unit and attach

chains or straps to lifting ring/hook “E” as shown in Figure 3-5.

Figure 3-5: Removing the Unit from Wood Pallet (Lifting)

Using the appropriate lifting equipment, hoist the unit from the wood pallet. The weight of each
models are as follows:

Model

Weight (lbs.)

AM399

291

AM500

302

AM750

511

AM1000

599

5. While unit is suspended, install the leveling feet “F” (Figure 3-6), to allow leveling the unit

after installation.

Figure 3-6: Installing the Leveling Feet

WARNING!

The floor onto which the unit is installed must
be capable of supporting the weight of the unit
or the unit and/or building may be damaged.