Mounting Procedure — DHIF
(Flanged heaters with control box)
1. At heater location, cut out a section of duct, or a new con-

struction lay out duct work to accommodate dimensions of
heater.

2. Form mounting flanges on cut edges of duct as shown in

Figure 17. Omit flange in side when terminal box overhangs.

3. Position heater in duct and attach duct lip to heater flanges with

sheet metal screws.

4. Attach control box to duct with sheet metal screws through the

mounting holes provided inside the control box.

NOTE: Where necessary, make provision to support weight of
heater. Any part of heater flange may be drilled for attaching hang-
er straps or duct.
5. Where necessary, joint between duct and heater flange may be

sealed with silicone gaskets or silicone sealant.

Mounting Procedure DHII
(Insert heaters with control box)
1.
Measure dimension “H” of duct heater (Figure 1) and mark the

duct with an outline for a rectangular hole with dimensions of
D-1

1

/

2

”. The D-1

1

/

2

” dimension is to be parallel to the direction

of air flow.

2. Increase D-1

1

/

2

” slot to D by forming a

3

/

4

” double lip on both

sides of the duct opening. (See Figure 18).

3. Slide heater into duct.
4. Attach control box to duct with sheet metal screws through the

mounting holes provided inside the control box and through
the brackets on the top and bottom of heater.

5. Where necessary, make provision to support weight of heater

and terminal box.

Mounting Procedure — DHRF
(Flanged heaters with compact terminal box)
1.
At heater location, cut out a section of duct, or on new con-

struction lay out duct work to accommodate dimensions of
heater.

2. Form mounting flanges on cut edges of duct as shown in

Figure 19.

3. Position heater in duct and attach duct lip to heater flanges with

sheet metal screws.

NOTE: Where necessary, make provision to support weight of
heater. Any part of heater flange may be drilled for attaching hang-
er straps or duct.
4. Attach control box to duct with sheet metal screws through the

mounting holes provided inside the control box.

5. Where necessary, joint between duct and heater flange may be

sealed with silicone gasket or sealant.

Mounting Procedure — DHRI
(Insert heaters with compact terminal box)
1.
Measure dimension “H” of duct heater (Figure 2) and mark the

duct with an outline for a rectangular hole with dimensions of
D-1

1

/

2

” x “H”. The D-1

1

/

2

” dimension is to be parallel to the

direction of air flow.

2. Increase D-1

1

/

2

” slot to “D” by forming a

3

/

4

” double lip on each

side of the duct. (See Figure 19).

3. Slide heater into duct.
4. Attach control box to duct with sheet metal screws through the

mounting holes provided inside the control box and through
the brackets on the top and bottom of heater.

5. Where necessary, make provision to support weight of heater.

-5-

MOUNTING

Self-Adhesive Gasket
Supplied with Heater and
Installed by Customer

Double
Lip

3/4"

3/4"

Duct

Sheet Metal
Screws

Control
Box

Sheet Metal
Screws

Mounting
Holes

W

W

H

H

D

Self-Adhesive Gasket
Supplied with Heater and
Installed by Customer

Double

Lip

Duct

H

W

3/4"

D

Self-Adhesive Gasket
Supplied with Heater and
Installed by Customer

Double

Lip

3/4"

Duct

Control
Box

Sheet Metal
Screws

Mounting
Holes

W

H

H

W

D

Self-Adhesive Gasket
Supplied with Heater and
Installed by Customer

Double

Lip

3/4"

Duct

D

3/4"

H

W

Figure 17

Figure 18

Figure 19

Figure 20

Advertising