24V Field Control Wiring Length and Size Requirements

Total Wire Length

Minimum Recommended Wire Size

150 ft

#18 gauge shielded wire

250 ft

#18 gauge shielded wire

350 ft

#14 gauge shielded wire

The manufacturer recommends for optimum temperature control performance that the

analog and digital inputs (CO

2

and air quality sensors) that are connected to the main

controller have a <3% wattage drop and be routed to the unit in one of the following

manners:
1) In separate conduits, isolated from 24 VAC controls and line voltage power to the

unit, OR

2) If the digital sensor wires are to be run in the same conduit as the 24 VAC control

wiring, the CO2, VOC, and display sensor wiring in Options CN7B, CN7C, and

RB5 must be completed using shielded cable and bundled separately from the 24

VAC control wiring. The shield must be drained at the unit and taped on the oppo-

site end.

Comply with the digital control sensor wire gauge and length requirements in the

table below.

Digital Control

Signal Wiring

Recommendations

and Requirements

Maximum

Sensor Wire

Length for less

than 1°F Signal

Error

Wire Gauge

Maximum Sensor Wire Length (Digital Control)

AWG

Feet

Meters

14

800

244

16

500

152

18

310

94

7.5.2 Specific Wiring

by Control Option

Depending on which field-installed control option was ordered, the unit will operate

whenever there is a call for fresh air (ventilation) from that control. Otherwise, the unit

is OFF.

• Option CN5 - Wall-mounted, Manual Start/Stop Switch

• Option CN7A - Time Schedule Clock with Manual On/Off Override Switch

• Option CN7B - CO

2

Sensor with Unit Control Hand/Off/Auto Switch

• Option CN7C - Indoor Air Quality (VOC & CO) with Hand/Off/Auto Switch

• Option CN7D - Occupancy Motion Switch with Manual On/Off Override

Switch

Wall Start/Stop Switch,

Option CN5

The wall-mounted, manual two-position key switch in Option CN5 will start or stop the

unit. Mount the 2-wire, 24V switch in a field-supplied, standard 2 x 4 electrical box.

Install the cover plate. Follow the wiring diagram to run the wires and make the con-

nections. Mount the start/stop switch on the wall.

START

STOP

START

STOP

2 Key Positions

KEY LOCK

POWER SWITCH

CN5

2-Position (start/stop)

Key Switch, P/N 260227

Cover, P/N 260229

Label, P/N 260228

Reference

Components and wiring

information for Option CN5.

8

3

=

field wiring

=

field connection terminal block in the

electrical compartment of the unit

FIGURE 21 - Option

CN5, Start/Stop Wall

Switch and Wiring

Connections

Time Clock Wall Switch,

Option CN7A

The compact wall-mounted time clock with manual

ON/OFF override will start or stop the unit. The

24-hour time clock schedule allows flexible week-

day and weekend start/stop times with a convenient

daylight savings update. A rechargeable battery

maintains the programming in a temporary power

outage.

The unit requires a 2-wire, 120V power

supply, external of the ventilation unit. As shown

in the wiring diagram, a switch relay converts the

time clock 120V output to a set of dry contacts. Two

Advertising