Automatic generator exerciser, Manual generator testing – Winco ASCO 165 2-Wire User Manual

Page 7

Advertising
background image

source acceptable lights

load transfer

test button

transfer switch on generator

(alternate source) light

transfer switch on utility

(preferred source) light

7

AUTOMATIC GENERATOR EXERCISER

The automatic generator exerciser automatically exercises

the generator for 20 minutes once every 14 days.

TO SET EXERCISER

Press and release the

Automatic Generator Exerciser but-

ton. After about 8 seconds the exerciser light flashes 14 times

to indicate that the exerciser has been set. The number of

flashes indicates the number of days until the next exercise pe-

riod (at approximately the same time the button was pressed).

TO DISABLE EXERCISER

Press and hold the

Automatic Generator Exerciser button

until the light above the button goes off (light flashes then

goes off). The exerciser is now disabled and the light is off.

TO ENABLE EXERCISER

Press and hold the

Automatic Generator Exerciser button

until the light goes off (light flashes then goes off). Exerciser

is now enabled. After about 8 seconds exerciser light flashes 14

times to indicate that the exerciser has been re–enabled.
Note: With a total power failure (utility failure and generator

fails to start) the exerciser must be reset after power is

restored.

set exerciser button

automatic generator exerciser light

MANUAL GENERATOR TESTING

GENERATOR TEST WITH LOAD TRANSFER

During this test a utility failure is simulated. The generator

starts and the load transfers to the generator. Then the load

retransfers back to the utility and generator stops.
1. Press and hold the

Push to Test button until the

GENERATOR acceptable light comes on and stays on

(the generator cranks and starts).

2. The automatic transfer switch waits 15 seconds to allow the

generator to warm up. Then it transfers the load to the

generator. The

TRANSFER

SWITCH on generator

(alternate

source)

light

comes on.

3. After 5 minutes the auto–

matic transfer switch re–

transfers the load back to

the utility. To bypass the
time delay, press and

release the

Push to Test

button again. The

TRANS–

FER SWITCH on utility

(preferred source) light

comes on.

4. After load retransfer the

generator will continue to

run unloaded for one min-
ute for engine cooldown.

Then it is stopped. The

GENERATOR acceptable

light goes off.

GENERATOR TEST WITHOUT LOAD TRANSFER

During the test the generator cranks and starts and the

GENERATOR light comes on (if it is acceptable). After

running for 20 minutes it stops. Throughout the test the load

remains connected to the utility (the automatic transfer

switch does not transfer the load to the generator).
1. Press and release (do not hold) the

Push to Test button.

The generator cranks and starts, and the

GENERATOR

acceptable light comes on and stays on.

2. The generator runs for 20

minutes. The automatic

transfer switch does not
transfer the load to the

generator. The

TRANS-

FER SWITCH on utility

(preferred source) light
stays on.

3. To bypass the time delay or

cancel the test, press and
release the

Push to Test

button again.

4. The generator stops and

the

GENERATOR accept-

able light goes off.

Advertising