3.9 BORE MILLING (Cy

c

le 208)

3.9 BORE MILLING (Cycle 208)

Cycle run

1

The TNC positions the tool in the spindle axis at rapid traverse FMAX
to the programmed set-up clearance above the workpiece surface
and then moves the tool to the bore hole circumference on a
rounded arc (if enough space is available).

2

The tool mills in a helix from the current position to the first
plunging depth at the programmed feed rate F.

3

When the drilling depth is reached, the TNC once again traverses
a full circle to remove the material remaining after the initial
plunge.

4

The TNC then positions the tool at the center of the hole again.

5

Finally the TNC returns to the set-up clearance at FMAX. If
programmed, the tool moves to the 2nd set-up clearance at FMAX.