Introduction

This instruction manual is intended to assist those involved

with the installation, operation and maintenance of Eagle

Model A100 pumps. It is recommended that this manual be

thoroughly reviewed prior to installing or performing any work

on the pump or motor.

I-A. Importance of Instructions

The design, material and workmanship incorporated in the

construction of Eagle pumps make them capable of giving

long, trouble–free service. The life and satisfactory service of

any mechanical unit, however, is enhanced and extended by

periodic inspection and careful maintenance. This instruction

manual was prepared to assist operators in understanding the

construction and correct methods of installing, operating, and

maintaining these pumps.

Study thoroughly Sections I, II, III, and carefully follow the

instructions for installation and operation. Sections IV, V, VI,

VII, and VIII are answers to trouble and maintenance questions.

Keep this instruction manual handy for reference.

I-B. Special Warnings

Eagle Pump and Compressor will not be liable for any damages

or delay caused by failure to comply with the provisions of this

instruction manual. This pump is not to be operated at speeds,

working pressures, discharge pressures, or temperatures higher

than nor used with liquids other than originally intended for,

without written permission of Eagle Pump.

I-C. Receiving Inspection—Shortages

Care should be taken when unloading pumps. If shipment is

not delivered in good order and in accordance with the Bill–of–

Lading, note the damage or shortage on both receipt and freight

bill. MAKE ANY CLAIMS TO THE TRANSPORTATION

COMPANY PROMPTLY.

SECTION I—GENERAL

Instruction sheets on various components as well as the

Instruction Book for the pump are included in the shipment.

DO NOT DISCARD!

I-D. Preservation and Storage

Eagle’s normal domestic shipping and storage preparation is

suitable for protecting the pump during shipment in covered

trucks. It also provides protection during covered storage at the

jobsite, and for a short period between installation and start-up.

If the pump is to be idle and exposed to the elements for

an extended period, either before or after installation, special

precautions are required. One approach is to provide special

preservatives and wrapping before shipment. However, after

installation the protective wrappings will have been removed.

Therefore, application of preservatives after installation is

considered a good practice.

The driver, coupling, and mechanical seal manufacturers should

be contacted for their recommendations on preservation and

protection procedures.

I-E. Handling Techniques

Care should be used in moving pumps. Pumps should not be

hoisted by eyebolts. These eyebolts are intended for removing

the back pull–out assembly for maintenance and inspection. An

assembled pump should be hoisted using a sling under suction

flange and under rear of bearing frame. Bedplate mounted units

should be hoisted using slings under bedplate below both pump

and driver.

II-A. Location

Pumping unit should be placed as close as practical to the

source of supply. Floor space and headroom allotted to the unit

must be sufficient for inspection and maintenance. Be sure to

allow for crane or hoist service.

II-B. Foundations

1. Grouted—Bedplate mounted units are normally grouted–in

on a concrete foundation, which has been poured on a solid

footing. This allows a permanent, vibration–absorbing base for

the unit. The location and size of foundation bolts are shown

on the outline assembly drawings supplied for the unit. Fig. 1

illustrates a typical foundation bolt installation.

2. Flexibly Mounted—Installation and leveling of the optional

flexibly mounted bedplate should be carried out in accordance

with assembly drawings supplied in the data package for the

unit.

SECTION II—INSTALLATION

Figure 1

LEAVE 3/4" TO11/2" UNDER

BEDPLATE FOR GROUT

WEDGES

DAM

WASTE

BEDPLATE

GROUT

LEAVE TOP OF

FOUNDATION ROUGH,

AND WET BEFORE

GROUTING.

CONCRETE

FOUNDATION