Ii-d. piping practices, Ii-e. alignment—preliminary – Eagle Pump & Compressor A100 ANSI PUMPS User Manual

Page 4

Advertising
background image

4

II-C. Leveling and Grouting of

Baseplate Initial Alignment Check

1. Put the unit in place on wedges located at four points as

shown in Fig. 2. Some long installations may require additional

wedges near center of bedplate.

2. Adjust wedges to level unit (approximately), placing unit

between 3⁄4” and 11⁄2” above foundation. Level or plumb suction

and discharge flanges. Then, bring the coupling halves into

reasonable alignment by adjusting the wedges as needed.

3. Make sure that the baseplate is not distorted and that final

accurate coupling alignment can be established within the limits

of movement of motor and by shimming motor if necessary.

4. Tighten foundation bolts finger tight. Build dam around

foundation and pour grout. Fill to level of grout hole making

sure that the areas under the pump and motor feet are filled

solid. Allow grout to harden at least 48 hours before further

tightening foundation bolts. Tighten pump hold down bolts.

II-D. Piping Practices

Guidelines for piping are given in the “Hydraulic Institute

Standards” and should be reviewed prior to pump installation.

All piping should be supported independently of, and line up

naturally with, the pump flanges. NEVER DRAW PIPING

INTO PLACE BY USE OF FORCE AT THE FLANGED

CONNECTIONS OF THE PUMP.

Both suction and discharge piping should be as short and direct

as possible to minimize friction losses. Foundation, pump and

driver hold–down bolts should be tightened prior to connecting

suction or discharge piping to the pump.

On units handling corrosives, the piping can be arranged to

allow flushing of the pump prior to opening of the unit for

servicing. After connecting suction and discharge piping to the

pump, rotate pump by hand to be sure that there is no binding.

II-E. Alignment—Preliminary

Alignment of the pump and driver is of extreme importance

for trouble–free mechanical operation. Alignment should be

obtained by adding or removing shims from under the motor

feet. The pump bearing frame foot should never be adjusted

to obtain alignment. The proper shimming is installed under

the bearing frame foot at the factory on units shipped with

bedplates. Changing the pump casing or bearing frame in the

field will require a reshimming of the frame foot. The proper

number of shims is installed when the pump shaft is level and

parallel to the bedplate surface. Proper shimming is achieved

by loosening frame foot and tightening casing foot. This should

create a gap between the frame foot and bedplate between 0

and .040 inches (1mm). This must be filled with shims and

the frame foot retightened. If this procedure is not followed,

mechanical problems can result. The final alignment is done

after the unit has been run under actual operating conditions.

The following are suggested steps for aligning the unit, prior to

initial startup.

1. Parallel Alignment: The unit is in parallel misalignment

when the shaft axes are parallel, but not concentric. During

initial alignment, vertical parallel alignment may be different,

due to thermal expansion of the unit at actual operating

conditions. The following is a suggested cold setting for motor

driven units:

Pumpage

Temperature

Above Ambient

Set Motor Shaft

Ambient

.002–.004” low (.05–.10 mm)

100° F.

.000–.002” high (.00–.05 mm)

200° F.

.004–.006” high (.10–.15 mm)

300° F.

.008–.010” high (.20–.25 mm)

400° F.

.012–.014” high (.30–.35 mm)

500° F.

.016–.018” high (.40–.45 mm)

2. To check the parallel alignment of “spider–insert” couplings,

place a straight edge across both hubs at four points, 90° apart

(see Fig. 3). To check the parallel alignment of flexible spacer

couplings, place a dial indicator on one hub and rotate that

hub 360° while taking readings on the outside diameter of the

other hub. Alignment occurs when indicator deflection does

not exceed .002” T.l.R. (see Fig. 4) of the recommended cold

setting in elevation and not more than .002” T.l.R. side to side.

To check angular alignment of a “spider–insert” coupling, use

calipers at 90° intervals on the circumference on the outer end

of hubs. When caliper measurements are identical, the unit is

in angular alignment. The correct gap between the hub and

insert will be given in the coupling manufacturer’s instructions

supplied for the pump.

To check angular alignment of flexible spacer couplings, place

a dial indicator on one shaft hub and rotate the hub 360°. Take

readings from the face of the other hub. Alignment is achieved

when deflection does not exceed .002” (see Fig. 5).

Figure 2

WEDGES

Advertising