SMA SI 3.0-11 Installation User Manual

Page 59

Advertising
background image

SMA Solar Technology AG

7  Electrical Connection

Installation Manual

SI30M-44M-60H-80H-IA-en-30

59

Checking the DC connection of the Sunny Island inverter

Checking connections AC1 and AC2 of the Sunny Island inverter

Test point

Test criterion

OK

Enclosure opening for DC

In the cable gland M32, the diameter of the DC power cable must

be 14 mm to 25 mm.

DC connection

Terminal lugs are pressed on firmly.

The bolted connection for fitting terminal lugs to the DC connection

is assembled as follows: head of M8x20 screw | spring washer |

fender washer | terminal lug | DC connection.

Terminal lugs are firmly fastened on the Sunny Island

(torque: 12 Nm).

DC power cable

The maximum length of cables from the battery via the BatFuse to

the Sunny Island is 10 m.

The conductor cross-section meets the cable requirements of

50 mm² to 95 mm² (for the recommended conductor cross-section,

see Section 7.4.1).

BatFuse

Fuse links are matched to the Sunny Island.

• SI3.0M-11: 80 A
• SI4.4M-11: 100 A
• SI6.0H-11: 160 A
• SI8.0H-11: 200 A

The cables are attached to the BatFuse with the required torque

(see BatFuse installation manual).

If installed, charge controllers and DC

loads

All charge controllers and DC loads are installed in accordance

with the manufacturer's specifications.

If installed, battery current sensor

The battery current sensor can be loaded with the maximum DC

current (see technical data of the battery current sensor).

Test point

Test criterion

OK

Enclosure openings AC1 and AC2

All enclosure openings are sealed with M25 cable glands or filler

plugs.

For an M25 cable gland, the cable diameter must be 9 mm to

18 mm.

Connections AC1 and AC2

All contact areas are not insulated.

All terminal levers are in the downward position.

All cables are securely clamped.