Cut the ceiling tile, Finish projector ceiling mount installation – Extron electronic PoleVault Systems PVS 400 User Manual

Page 17

Advertising
background image

2-5

PoleVault Systems Installation • Installation — Stage 1

4. Cut the ceiling tile

a.

Mark the location of the PCM 240 on the T-bar, before

removing it. This aids putting it back in the correct

location when the tile is replaced.

T

Mark the screen direction on back of the tile (e.g. with

an arrow or “to front”) to help orientation of tile when
replacing it after cutting.

b.

Measure the distances X and Y (see figure) from the inner

vertical section of the front and left T-bar runners to the

center of the Pipe Adapter Plate.

c.

Using these dimensions, mark and cut a hole for the

PMP in the ceiling tile.

T

Place the tile on a box, mark hole center on the

underside of the tile. Use a hole saw bit to start to cut
the hole by hand (turning bit counter clockwise) to
avoid damaging the tile. When the drill bit is through
the tile, turn the tile over and finish cutting from the
top side.

5. Finish Projector Ceiling Mount

installation

a.

Loosen the set screws and unscrew the UPB 25 from the

mounting pole. Do not remove the projector bracket

from the projector.

b.

Loosen the PCM 240 ‘s set screw and remove the

mounting pole, then remove the PCM 240.

c.

Replace the cut ceiling tile, checking the orientation to

align the hole with the PCM 240.

d.

Replace the PCM 240 over the ceiling tile and screw

the mounting pole (with the access hole uppermost) up

through the hole into the mounting plate. Tighten the set

screws.

T-bar

X"

Y"

Minimum and
Maximum
Throw Distance Marks

4b

Take measurements with the PCM 240

on the T-bar

5d

Screw the PMP into the mounting plate

(viewed from below)

4c

Mark and start cutting the hole on the

underside. Finish on the top side.

Advertising
This manual is related to the following products: