6

OVLERQ*C OVLSRQ*C OVLESRQ*F OVLSERQ*F

97793C - 10/01

Figure 9 – OVL-II ER-Q/OVL-II SR-Q Rough-In

Figure 10 – Rough-In Assembly

Single-Station Mounting Frames

Models

OVL-II ER-Q – OVL-II SR-Q

1. Cut a rectangular wall opening 18-3/4”

(475 mm) W x 37-3/4” H (959 mm) and 4-1/2” (114 mm)

above the floor line (see Figure 10). The dimensions

are required to obtain proper rim and bubbler heights

for compliance with ANSI standard A117.1.

2. Reinforce the wall opening on all sides to adequately

support the water fountain. This reinforcement must

support up to 150 lbs. static load and provide a

means for securing the frame assembly in place.
NOTE: Building construction must allow for adequate

air flow on both sides and top of remote

chiller unit. Minimum of 4” (102 mm) is

required.

3. Install plumbing and electrical rough-ins. A junction

box for a (3) wire, 10 amp branch circuit is provided on

the inside of the chiller. (Standard 120 Volts, 60 Hz,

and single phase.)

4. Remove frame and related hardware from

packaging. Release the two shelf rods by cutting

cable ties.