2-8. DE-ICING AND CLEANING
WATER DRAINAGE

A floor trench, located in front of the door is recommended, with a
floor drain nearby, because of the quantity of water used in
cleaning.

For sanitary reasons, do not install a drain in the floor of the
blast chiller.

To ensure proper performance:
• When sizing a single condensing system for multiple blast chill-

ers, the total BTU’s of all blast chillers should be considered

• An evaporator pressure regulator is required for combinations of

freezers and chillers on the same system

• Do not install a single condensing unit for more than 1 blast

freezer if they are to operate simultaneously; always install
separate condensing units for each blast freezer

• In addition to the compressor, condenser, and receiver, the unit

should be fitted with:
- low ambiant control
- high pressure, pressure controller
- automatic pump-down controller
- drier
- sight glass
- line
- insulation and refrigeration load

• Depending upon the ratings, the installation of a separate oil

separator, liquid valve, suction trap, etc, is also recommended

• Remote condensing unit compressors for blast chillers can be of

any type, but blast freezers, or blast chiller/freezers must use
semi-hermetic compressors, not hermetic

• Local area climate and codes help in detemining the size of the

condensing unit; use the maximum average temperature of the
summer, not the hottest temperature, or the unit will be over-
sized and over-priced for only a couple of weeks of hot
weather

• The condensing unit should have a separate electrical line

protected by a fuse or circuit breaker of the proper rating

2-9. REMOTE CONDENSING
UNITS INFORMATION

505