Power supply
Figure 14: Indicators on the power supply unit
5.1.6
Completing the task
Ê
Perform the following procedures to complete the task:
1. Close the rear door of the rack, see
"Closing the rack door" on page 51
5.2
Replacing a hot-plug power supply unit
V
CAUTION!
When replacing a non-defective hot-plug power supply unit in a non-
redundant configuration, the server must be switched off first.
5.2.1
Required tools
●
Starting and completing the task:
–
key for the rack doors (if applicable)
●
Replacing the power supply unit: tool-less
Trained personnel
/