MITSUBISHI ELECTRIC TG-2000A User Manual

Page 91

Advertising
background image

88

c . Check to see if the total of the division results of all the indoor units matches the total of the watt

hour meter.

Because division errors occur, a difference less than (the number of blocks × 0.1) kWh is
deemed OK.
If the difference exceeds (the number of blocks × 0.1) kWh then check the following settings and
rectify the problem.

• Charge block setting (block setting)
• Outdoor unit to watt hour meter relationship
• Indoor unit to watt hour meter relationship


d. Check that the standard charge portion is included in the block settlement amount of the

settlement results.
Block settlement amount = (total of block indoor units division electric amount totals) × charge
unit + standard charge
Because settlement errors occur, a difference less than number of blocks × minimum exchange
unit is deemed OK.
When the difference exceeds (number of blocks × minimum exchange unit) then check the
following settings and rectify the problem.

• Charge block setting (block setting)
• Standard charge setting










To make the check sheets easy to read, allocate 1 check sheet page for each installation floor unit or
G-50A unit.

(8) Change to actual operation setting

After the charging test run check is completed, restore the regular field settings.








Note:

• Only judgment standard d can be recalculated and rechecked.

Maintenance Tip:

• After the charging test run check, check the result of the print out of the settlement day

calculation for day 1.

• If the system is modified, always check the calculation results of the next settlement day or

one day after the change and 10 days after the change.

N o t e :

• During charging test run, set the items shown below to the test run value. Set them to the

value to be used.

Charge setting, standard charge setting, settlement date setting