2. In the Node pane, click the icon of the node you want to verify
3. Click the

″

Notebook

″

icon on the tool bar

v

When the Notebook window opens, make certain that the

″

Node Status

″

tab is selected

4. The

″

Node failure:

″

attribute displays the status of the node supervisor

v

″

No

″

displayed in a green box indicates that the node supervisor has not failed and the supervisor

is responding

v

″

Yes

″

displayed in a red box indicates that the node supervisor has failed and it is not responding

Note: Clicking

″

Help

″

in the Notebook window’s lower right corner displays attribute descriptions.

Frame supervisor verification

From the Hardware Perspectives window:
1. Unless you have saved display settings, the Hardware Perspective does not open with a frame pane

displayed. To open a frame pane:

a. Click the

″

Add Pane

″

icon on the tool bar

v

The Add Pane dialog box opens

b. From the

″

Pane Type

″

pull down, select

″

Frames and Switches

″

c. Select your choice of adding the pane to the current window or to a new window

d. If desired, enter a new pane title

e. Click

″

OK

″

to open the pane and close the dialog box

v

You may repeat these steps to add additional frame panes

2. In the Frame and Switch pane, click the icon of the frame you want to verify
3. Click the

″

Notebook

″

icon on the tool bar

v

When the Notebook window opens, make certain that the

″

Frame Status

″

tab is selected

4. The

″

Controller responds:

″

attribute displays the status of the frame supervisor

v

″

OK

″

displayed in a green box indicates that the frame supervisor is responding

v

″

No response

″

displayed in a red box indicates that the frame supervisor is not responding

Note: Clicking

″

Help

″

in the Notebook window’s lower right corner displays attribute descriptions.

Switch supervisor verification

From the Hardware Perspectives window:
1. Unless you have saved display settings, the Hardware Perspective does not open with a switch pane

displayed. To open a switch pane:

a. Click the

″

Add Pane

″

icon on the tool bar

v

The Add Pane dialog box opens

b. From the

″

Pane Type

″

pull down, select

″

Frames and Switches

″

c. Select your choice of adding the pane to the current window or to a new window

d. If desired, enter a new pane title

e. Click

″

OK

″

to open the pane and close the dialog box

v

You may repeat these steps to add additional switch panes

2. In the Frame and Switch pane, click the icon of the switch you want to verify

v

A switch icon is displayed next to the frame icon only if a switch is installed in the frame

3. Click the

″

Notebook

″

icon on the tool bar

v

When the Notebook window opens, make certain that the

″

Switch Status

″

tab is selected

4. The

″

Node failure:

″

attribute displays the status of the switch supervisor.

v

″

No

″

displayed in a green box indicates that the switch supervisor has not failed and the

supervisor is responding to communication from the frame supervisor.