Adjustable height head installation – Quartz QZ3111 User Manual

Page 9

Advertising
background image

Quartz Thermo installation guide

page 9

Ensuring the fixing lugs and locating pins

are correctly aligned, carefully place the

valve end cap onto the on/off lever and click

into position.

23

Adjustable height head installation

Prepare pipe work from the shower valve to

the required position for the hose outlet using

a ø15mm copper pipe. Slide the 15mm gripper

ring down the projecting pipe up to the wall

face.

1

Trim the projecting pipe to a length of 15-22mm using a rotary type cutter.

If a hacksaw is used, the pipe end must be carefully de-burred and chamfered.

2

Clean and lubricate the pipe using a suitable (silicone based) lubricant.

3

Remove the wall outlet cover plate and carefully slide the wall outlet onto the

projecting pipe. Turn to the required position and mark the screw holes on the

wall face.

4

Remove the wall outlet and drill and prepare

suitable wall fixings. Ensure the projecting pipe

is clean and lubricate again if necessary.

Refit the wall outlet and secure it to the wall

using the screws provided.

5

Refit the wall outlet coverplate.

6