REFRIGERANT PIPING AND EVACUATING

„

Refrigerant Piping

• The connecting sections of the refrigerant pipes are

provided at the positions in the figure below.

1. Use copper pipe with 0.03” (0.8 mm) or more

thickness.
(In case pipe size is Ø5/8” (15.9 mm), with 0.04” (1.0
mm) or more.)

2. Flare nut and flare works are also different from

those of the conventional refrigerant.
Take out the flare nut attached to the main unit of the
air conditioner, and use it.

REQUIREMENT

When the refrigerant pipe is long, provide support
brackets at intervals of 8’2” - 9’10” (2.5 - 3 m) to clamp
the refrigerant pipe. Otherwise, abnormal sound may
be generated.

CAUTION

IMPORTANT 4 POINTS FOR PIPING WORK
1. Remove dust and moisture from the inside of the

connecting pipes.

2. Tight connection (between pipes and unit)
3. Evacuate the air in the connecting pipes using

VACUUM PUMP.

4. Check the gas leakage. (Connected points)

„

Pipe size

„

Permissible Piping Length
and Height Difference

They vary according to the outdoor unit.
For details, refer to the Installation Manual attached to
the outdoor unit.

Flaring

• Cut the pipe with a pipe cutter.

Remove burrs completely.
Remaining burrs may cause gas leakage.

• Insert a flare nut into the pipe, and flare the pipe.

As the flaring sizes of R410A differ from those of
refrigerant R22, the flare tools newly manufactured
for R410A are recommended.
However, the conventional
tools can be used by adjusting
projection margin of the
copper pipe.

Projection margin in

flaring: B (Unit: in (mm))

Rigid (Clutch type)

Flaring dia. meter size: A (Unit: in (mm))

* In case of flaring for R410A with the

conventional flare tool, pull it out approx.

0.02” (0.5 mm) more than that for R22 to

adjust to the specified flare size.

The copper pipe gauge is useful for

adjusting projection margin size.

Model

name

RAV-

SP180

type

SP240, SP300,

SP360, SP420

type

Pipe size

Gas side

1/2"

(12.7 mm)

5/8"

(15.9 mm)

Liquid side

1/4"

(6.4 mm)

3/8"

(9.5 mm)

Rear side

* When using the drain

pump kit sold separately,

the pipe can be drawn out

only from the upper side.

Upper side

Right

Outer dia. of

copper pipe

R410A tool used

Conventional

tool used

1/4” - 5/8”

(6.4 - 15.9)

0 - 0.02”

(0 - 0.5)

0.04” - 0.06”

(1.0 - 1.5)

Outer dia. of copper pipe

Imperial

(Wing nut type)

1/4” (6.4) or 3/8” (9.5)

0.06” - 0.08” (1.5 - 2.0)

1/2” (12.7) or 5/8” (15.9)

0.08” - 0.1” (2.0 - 2.5)

Outer dia. of copper pipe

A

1/4” (6.4)

0.36” (9.1)

3/8” (9.5)

0.52” (13.2)

1/2” (12.7)

0.65” (16.6)

5/8” (15.9)

0.78” (19.7)

B

+0