1.

Before beginning the SpeedBrake

installation, locate The Palm Tungsten

E2 Power PDA in your kit. It will need

to be charged for a minimum of one

hour before the unit will function.

Charge the unit with the supplied

Ac-outlet wall charger. The unit will be

fully charged in one to two hours.

2.

Disconnect the negative (ground)

cable from the battery (or batteries, if

there are two) before beginning work.

Secure the cables so that they do not

come in contact with the battery posts

during the installation.

3.

Locate the Banks SpeedBrake wire

harness in your kit. Start By placing

the wire harness near the under hood

fuse box.

4.

Install the ground ring terminal on

the SpeedBrake wire harness onto the

bolt on the fire wall. See figure 1.

5.

Remove the fuse box cover to

access the fuses on the electrical

center and set aside.

6.

Locate mini-fuse for the Body

control Module (TBc IGN1) and remove

it. See figure 2.

7.

Install the mini-blade fuse tap onto

the removed mini fuse as shown in

figure 3. Re-install the mini fuse with

the attached blade tap into the fuse

box.
Note: install the fuse tap in the

Body Control Module (tBC IGN1) spot

closest to the firewall. this is the “hot”

side of the circuit. See Figure 2.

8.

Locate the fuse connector wire on

the SpeedBrake wiring harness and

connect it to the mini-blade fuse tap.

9.

Replace the fuse box cover and

make sure not to pinch the fuse

connector wire.

10.

Locate the black wire harness

locking connectors between the brake

fluid reservoir and the air conditioning

compressor. Lift the gray connector

locks and disconnect the 24-pin

connector pair. See figure 1.

Figure 1 Grounding location & 24-Pin Intercepting Connectors