21.

On the 2002-03 F-series

models only, it is necessary to

relocate the factory-installed

frame-mounted hanger pin that is

located behind the transmission

crossmember.
A. Remove the two (2) nuts that hold

the frame-mounted hanger pin to

the frame rail, save for reinstallation

later. Remove the frame-mounted

hanger pin from vehicle.
B. Remove the two (2) 8mm studs

from the frame-mount hanger pin.
C. Reinstall the frame-mounted

hanger pin using the two (2)

5

8

” long

steel spacers, two (2) 8mm x 1.25 x

45mm bolts and the two (2) 8mm nuts

(removed in Step A above). See Figure

3 for proper assembly sequence.

Torque fasteners to 18 ft-lb.

22.

Reusing the saved V-band clamp

previously put aside, loosely clamp

the upper portion of the turbine

outlet pipe to the warm-up valve or

the Banks Brake on the turbocharger.

Do not tighten at this time.

23.

Place a 4” exhaust clamp on the

turbine outlet pipe. Install the front

intermediate pipe onto the turbine

outlet pipe. Place a 4” exhaust clamp

on the front intermediate pipe (see

Figure 5).

24.

For Standard Cab long-bed

vehicles: It will be necessary to cut

43

4

” off the rear intermediate pipe

supplied in the kit. The hanger will

be removed with the unused portion

of the pipe (see Figure 4). Install the

rear intermediate pipe.
Install the rear intermediate pipe as

supplied (no cut required).
Install the rear intermediate pipe.

Place a 4” clamp on the end of the

rear intermediate pipe and install the

extension pipe (P/N 53513).
Remove the rear frame mounted

hanger and install the supplied frame

mounted hanger in its place, using

the two 8mm x 30mm hex bolts

supplied and re-using the two 8mm

nuts previously removed (see Figure

6). Install the rear intermediate pipe.

Place a 4” clamp on the end of the

rear intermediate pipe and install the

extension pipe (P/N 53514).
Install the rear intermediate pipe.

Place a 4” clamp on the end of the

ear intermediate pipe and install the

extension pipe (P/N 53515).

25.

If installing a Git-Kit, place a 3

1

2

clamp on the adapter provided and

install it on the stock intermediate or

extension pipe.

26.

Place the front hanger clamp

on the inlet end of the Banks

Monster muffler and install it onto

the intermediate pipe or extension

pipe. Note the inlet labeling on the

Monster muffler. Be sure the Banks

Monster embossing on the muffler is

level with the frame.
Insert the front hanger pin into the

rubber hanger at the front of the

muffler.

27.

slide the rear hanger clamp over

the outlet of the muffler with the

hanger pins facing forward. Insert the

hanger pin(s) into the corresponding

rubber hanger(s).
install a 4” clamp onto the muffler

outlet.
Install the Banks Monster tailpipe

over the rear axle housing and into

the outlet of the Monster muffler.

28.

Slip the 5” Monster tailpipe tip

on with the drain hole facing down

and Banks logo facing up. Keep the

wrapping on for now. For a Fleet-

side truck the 5” tip should be hung

1” past the end of the tailpipe. For

a dually, the tip should be 3

1

2

” past

the end of the tail pipe. Snug up the

clamp.

Section 4

ExHAuST INSTALLATION (PART 2 OF 2)

Figure 3

8

96334 v.5.0