Page 11
strap. Be sure the torque converter
is stable inside the transmission.
18.
Place a suitable drain pan under
the front of the transmission.
CAUTION: Verify that the
transmission is secured to the
lifting device. When the torque
converter is removed, the
transmission’s center of gravity
will shift and the transmission may
become unstable.
19.
If previously used, remove the
torque converter holding tool. Evenly
pull on the torque converter to
remove it – avoid wiggling or cocking
the converter sideways as much as
possible to prevent damage to the
transmission input shaft and seals.
Note: Inspect the oil seal on the front
pump of the transmission. If there are
signs of leakage or damage, the seal
should be replaced prior to installing the
new torque converter.
20.
carefully remove the Banks Billet
Torque converter from the shipping
container. Be careful not to damage
the shipping container, as it will be
used to return the factory torque
converter to Gale Banks Engineering.
21.
To avoid pump seal damage
during converter installation, inspect
the Banks Billet Torque converter
hub and hub drive notches for sharp
edges, burrs, scratches or nicks. It
may be necessary to polish hub and/or
notches with 320⁄400 grit sandpaper
and crocus cloth – clean the converter
afterwards to remove any foreign
particles as necessary.
22.
Position the Banks Billet
Torque converter with the drive hub
up and pour one (1) quart of the
Figure 4
96772 v.6.0