Banks Power Ford Trucks: (Diesel ’99 - 03 7.3L Power Stroke) Powertrain- Banks Billet Torque Converter '99-03 Trucks equipped with E4OD or 4R100 Transmissions User Manual

Page 12

Advertising
background image

manufacturer’s specified transmission

fluid into the drive hub. Use a small

amount to coat the splines of the input

shaft protruding from the transmission.
CAUTION: When installing the

Banks Billet Torque Converter, be

careful to not damage the pump

gear O-ring or hub seal.

23.

Lift the Banks Billet Torque

converter and position it in front of

the transmission input shaft. Turn the

torque converter as needed to index

properly and engage the transmission

input shaft splines, then carefully

work the torque converter onto the

transmission input shaft until it is

recessed behind the front transmission

mounting flange. Use a straightedge

to verify there is a gap between the

converter pilot hub face and housing

(see Figure 5). This ensures that the

Torque converter is fully engaged to

the input shaft and the drive hub is

sealed properly.

24.

Retain the torque converter with

the converter holding tool, if available.

25.

Before installing the transmission

into the vehicle, Gale Banks

Engineering recommends flushing and

thoroughly cleaning the transmission

cooler, lines, and cooler bypass valve.

Lubricating the converter pilot hub

with multipurpose grease is also

recommended.

26.

Position the transmission

near the engine and remove the

converter holding tool, if used. Align

the converter studs with the engine

flexplate. Install the transmission to

the engine.

27.

Reinstall the six (6) transmission

mounting bolts through the

transmission mounting flange and into

the engine. Torque evenly to 45 ft-lbs.

28.

If previously removed, reinstall

any disconnected exhaust system

components.

29.

Reinstall the transmission

crossmember onto the frame rails.

Reinstall and torque the crossmember

bolts to 60 ft-lbs (see Figure 4).

30.

Rotate the torque converter and

install the NEW (supplied) converter-

to-flexplate

3

8

”-24 nuts. Evenly torque

the nuts to 30 ft-lbs (see Figure 3).

31.

Reinstall the inspection cover and

torque the bolts to 15 ft-lbs.

32.

Verify the transmission is secured

to the crossmember and remove the

transmission hoist.
Note: The transmission fluid,

transmission fluid filter and pan gasket

should be serviced at this time. Follow

the instructions in the vehicles owner’s

manual for servicing the transmission.

33.

For 4x4 models, reinstall the

transfer case.
A) Hoist the transfer case to the

extension housing. Reinstall the six (6)

mounting bolts and torque to 37 ft-lbs.
B) Reconnect the three (3) position

switch harness connector and

gearmotor encoder harness

connectors.
c) Align and reinstall the front

driveshaft to the transfer case.
D) Reinstall the manual shift linkage

and remove the transfer case hoist.

34.

Re-align and re-attach the front of

the rear driveshaft to the transmission

or transfer case output shaft / flange.
On flanged models, only tighten the

attachment bolts finger-tight at this

time.
For models equipped with a two (2)

piece driveshaft, re-install the center

bearing support and hand-tighten the

mounting bolts.

10

96772 v.6.0

Advertising