PNEG-1722 Series II Sweep Protected Cord Slip Ring Sump
17
15. Wire the multi-conductor cord to the slip ring using the fork terminals provided in the
following manner.
1. Thermal protection leads
a. Wire the “P1” lead from the control panel to ring “1”.
b. Wire the “P2” lead from the control panel to ring “2”.
2. Drive motor leads
a. Wire the three (3) power leads to rings “3”, “4” and “5”.
b. Wire the ground lead to ring “9”.
3. Auger motor leads
a. Wire the three (3) power leads to rings “6”, “7” and “8”.
b. Wire the ground lead to ring “9”.
16. Replace the protective housing onto the slip ring.
17. Feed the multi-conductor cord through the slip ring shield and attach the slip ring shield to the cross
brace assembly using sixteen (16) 1/4" x 1" hex bolts, flat washers, lock washers and nuts.
18. Feed the multi-conductor cord through the lower shroud assembly and through the drilled conduit
exit hole in the sump wall.
19. Slide the lower shroud assembly into the slip ring shield.
Figure 4E