Series 2000 Vane Axial Heater

HEATER INSTALLATION

Air Pressure Switch and

Temperature Sensor Box

Installation

1. Using air switch box as a

guide, mark 2 holes on ple-
num side wall appproximately
24" to right of transition cen-
tered up and down in plenum.

2. Drill air switch filter hole 5/8"

diameter for snug fit. Drill tem-
perature sensor hole 5/8" or
larger to accommodate mounting
nut.

3. Mount Box to Bin using (4)

self drilling screws

4. Caulk between housing and side-

wall to seal.

Air Switch Box Assembly

1. Mark location on transition

one (1) foot up from the bot-
tom (entrance collar) and cen-
tered in the transition.

2. Drill or knock out 7/8" diam-

eter hole on marked location.

3. Install transition hi-limit using

supplied self drilling screws.

Transition Hi-limit Installation

Figure 1: The transition connecting the Series 2000 Heater to the bin with

the plenum sensor in place.