J85568E-1 Secondary DC Mini-Distribution Bay

Issue 6 January 2008

Installation 5 - 1

5

Installation

Safety

Read Section 4, Safety, carefully before installing the J85568E-1
Mini-Distribution Bay.

Tools and
Materials
Required

The following tools are required to install the Mini-Distribution
Bay:

•

Equipment to handle shipping container, remove
Mini-Distribution Bay unit or framework, and erect unit in
final position (minimum lifting capacity of 220 pounds)

•

Common electrician’s hand tools, including jeweler’s
screwdriver, electrical tape, wire cutters, and strippers for

8 AWG to 750 MCM

•

Common mechanic’s hand tools, including flat blade
screwdriver, socket and torque wrenches for 1/4-inch and
3/8-inch bolts, and a crowbar for uncrating unit

•

Proper crimping tools and dies for connectors. The
connectors specified are WP-91412, which may be installed
with compression tools made by Thomas & Betts using
color coded dies

•

3/4-inch drill to bore holes for floor anchors (List A only)

•

Anchor bolts (List A only)

•

22-26 gauge stranded or solid wire for connecting alarms

•

Terminal lugs for terminating distribution and load cables

•

WP-92461 fuses and 1/2-ampere GMT alarm fuses
(comcode 401231501) or circuit breakers