3.3.9 Standard installation procedure

NOTE

Ensure that the UPS is isolated prior to installation; no live input source may be
connected to the UPS during the installation procedure. Open all the input/output
switches/breakers on the power distribution and ensure no one is able to close
them during this installation step.

fig. 3.3.9.a

fig. 3.3.9.b

1. In case of Optional Distribution Unit

please follow instruction at section 6.1,
otherwise proceed with step 2.

2. Remove the terminal cover (fig. 3.3.9.a /

3.3.9.b).

3. Punch out the appropriate holes in the

terminal cover. Secure the input/output
cables using glands, according to
fig. 3.3.9.c.

4. Input. Connect the mains supply wires to

the terminals “L1-L2” (Line) and “N”
(Neutral) and the ground wire to terminal

“ ”. Ground connection is essential!
(fig. 3.3.9.d).

5. Output. Connect the load wires to the

terminals “L1-L2” (Line) and “N” (Neutral)
and the ground wire to terminal “ ”.

Ground connection is essential!
(fig. 3.3.9.d).

fig. 3.3.9.c

5/6 kVA

8/10 kVA

NOTE

Localize on figure 3.3.9.d proper terminals based on the desired input/output voltage.
For 8/10 kVA models use 6 AWG 75°C (167°F) copper wires, 22 lb-in fixation torque force.
For 5/6 kVA models use 10 AWG 75°C (167°F) copper wires, 20 lb-in fixation torque force.

fig. 3.3.9.d

fig. 3.3.9.e

5/6 kVA

8/10 kVA

modifications reserved

18

User manual GT Series 5/6/8/10 kVA UPS 1.0 (US)