7.4.2 Internal battery replacement (for 8/10 kVA models)


In case of battery failure, please proceed with the following steps to replace that:

NOTE

During battery replacement the UPS will not be able to support the load if a mains

failure occurs! It is recommended to switch off the load

(see section 4.3.2) before

battery manipulation

.



1. Remove the 2 lower UPS

front cover from the cabinet
by gently pulling them out.

2. Remove the battery grille by

loosening the three
mounting screws (fig. 7.4.2.a).

3. Disconnect DC cabling from

battery pack connectors
(fig. 7.4.2.b).

4. Grab hold of the battery

packs and slide them out
(fig. 7.4.2.b). Be careful during
this operation and consider
the weight of the battery.

5. Unpack the 2 new battery

packs from their carton
boxes.

6. Place the battery packs side

by side in the battery
compartment.

7. Fix the 2 battery brackets

with the screw set to hold
battery packs into the
cabinet (see section 3.3.4).

8. Connect the DC connectors

of each battery pack.

9. Fix the battery grille in front

of the battery compartment
with 3 screws.

10. Mount the two front covers

fig. 7.4.2.a

fig. 7.4.2.b

8/10 kVA

8/10 kVA


NOTE

To avoid battery malfunction, in case of additional batteries connected, all battery packs
have to be replaced! It’s not possible to replace only 1 pack. Avoid connection between
new and old battery packs.