3.5 VENTILATION AND COOLING

Fig. 3.5-1 Installation on plain floor

Fig. 3.5-2 Installation on raised floor



The heat produced by the UPS is transferred to the environment by its ventilation.

Air inlets for UPS ventilation are located on the front of the UPS, while air outlets are on top of the
cabinet.

A suitable ventilation or cooling system must be installed to extract the heat from the UPS room.

NOTE !

Do not put anything on the top of the cabinet.



Air filtration systems could be required when the UPS operates in a dirty environment.

Contact your Dealer or the nearest Service Center for appropriate solutions.

In order to prevent overheating of the UPS, the available air intake flow rate must exceed the total air
exhaust flow rate requirement of the UPS system.

The below table indicates the heat dissipation at full load at PF = 0.8 lag. and charged battery, up to
3,280 ft (1,000 m) altitude, for cooling air 77°F (25°C) to 86°F (30°C).

Losses

Cooling air flow

UPS rating

BTU / hr

kW

CFM

m

3

/ h

SG Series 10 kVA

3,036 0.89 135 230

SG Series 20 kVA

6,751 1.98 301 512

SG Series 30 kVA

8,104 2.37 361 614

SG Series 40 kVA

10,808 3.17 482 819