3.9 RPA PARALLEL SYSTEM CONNECTION

WARNING !

This operation must be performed by trained personnel before the initial start-up.

ENSURE THAT THE UPS INSTALLATION IS COMPLETELY POWERED DOWN.


3.9.1 Power wiring of parallel units

To guarantee good Load sharing between the units of a parallel system, we recommend that the cable
length from the input distribution board (5) to the output distribution board (10) is equal for each unit
(a+b = c+d = e+f = g+h = i+l = m+n = o+p = q+r).

Tolerance: +/-10%.

The AC input power of the Bypass must be the same for all units of the parallel system - no phase shift
allowed between units.

NOTE !

It is strongly recommended that no transformers, automatic circuit breakers or fuses
should be inserted between the unit’s output and the Load
common bus bars.
However, it is recommended that a disconnection or isolation switch is installed in
order to totally isolate a unit if needed.


1

= Rectifier

2

= Inverter

3

= Automatic

Bypass

4

= Manual

Bypass

5

= Input

Utility

Distribution

6

= Unit Output Load

External Battery fuse or
MCB

7

=

8

= External

Battery

Common bus-bar and
Output Load Distribution

9

=

= UPS Number 1

2

= UPS Number 2

3

= UPS Number 3

4

= UPS Number 4

5

= UPS Number 5

6

= UPS Number 6

7

= UPS Number 7

Fig. 3.9.1-1 Power wiring of RPA Parallel System

8

= UPS Number 8

Modifications reserved

Page 36/45

OPM_SGS_ISG_10K_40K_0US_V040.doc

Installation Guide SG Series 10 –20 – 30 - 40 kVA