Xylem AC8584C Series HSCS Base Mounted Centrifugal Pumps User Manual

Page 6

Advertising
background image

The foundation should be pour

ed without interruption to within

1

/

2

to 1

1

/

2

inches of the finished height. The top surface of the

foundation should be well scored and grooved before the
concrete sets; this provides a bonding surface for the grout.

Foundation bolts should be set in concrete as shown in Figure
4. An optional 4-inch long tube around the bolts at the top of
the concrete will allow some flexibility in bolt alignment to
match the holes in the base plate. Allow enough bolt length for
grout, shims, lower base plate flange, nuts and washers. The
foundation should be allowed to cure for several days before
the base plate is shimmed and grouted.

9. Base Plate Setting (Befor

e Piping)

NOTE: This pr

ocedure assumes that a concrete foundation

has been prepared with anchor or hold down bolts extending
up ready to receive unit. It must be understood that pump and
motor have been mounted and rough aligned at the factory. If
motor is to be field mounted, consult factory for recommenda-
tions. Bell & Gossett cannot assume responsibility for final
alignment.

a. Use blocks and shims under base for support at anchor

bolts and midway between bolts, to position base
approximately 1" above the concrete foundation, with studs
extending through holes in the base plate.

b. By adding or removing shims under the base, level and

plumb the pump shaft and flanges. The base plate does not
have to be level.

c. Draw anchor nuts tight against base, and observe pump

and motor shafts or coupling hubs for alignment. (Tem-
porarily remove coupling guard for checking alignment.)

d. If alignment needs improvement, add shims or wedges at

appropriate positions under base, so that retightening of
anchor nuts will shift shafts into closer alignment. Repeat
this procedure until a reasonable alignment is reached.

NOTE: Reasonable alignment is defined as that which is

mutually agree upon by pump contractor and the accepting
facility (final operator). Final alignment procedures are cov-
ered under “Alignment Procedures.”

e. Check to make sure the piping can be aligned to the pump

flanges without placing pipe strain on either flange.

f. Grout in base plate completely (See “Grouting Procedure”)

and allow grout to dry thoroughly before attaching piping to
pump. (24 hours is sufficient time with approved grouting
procedure.)

10. Gr

outing Procedure

Gr

out compensates for uneven foundation, distributes weight

of unit, and prevents shifting. Use an approved, non-shrinking
grout, after setting and leveling unit (See Figure 5).

a. Build strong form around the foundation to contain grout.

b. Soak top of concrete foundation thoroughly, then remove

surface water.

c. Base plate should be completely filled with grout.

d. After the grout has thoroughly hardened, check the founda-

tion bolts and tighten if necessary.

e. Check the alignment after the foundation bolts are

tightened.

f. Approximately 14 days after the grout has been poured or

when the grout has thoroughly dried, apply an oil base paint
to the exposed edges of the grout to prevent air and mois-
ture from coming in contact with the grout.

11. See ANSI/OSHA Coupler Guar

d Removal/Installation

(next page)

12. Alignment Pr

ocedure

NOTE:

Permissible misalignment will vary with the make of

coupling. Consult coupling manufacturer’s data when in
doubt.

Allowances are to be made for thermal expansion during cold
alignment, so that the coupling will be aligned at operating
temperature. In all cases, a coupling must be in alignment for
continuous operation. Even though the coupling may be lubri-
cated, misalignment causes excessive wear, vibration, and
bearing loads that result in premature bearing failure and
ultimate seizing of the pump. Misalignment can be angular,
parallel, or a combination of these, and in the horizontal and
vertical planes. Final alignment should be made by moving
and shimming the motor on the base plate, until the coupling
hubs are within the recommended tolerances measured in
total run-out. All measurements should be taken with the
pump and motor foot bolts tightened. The shaft of sleeve
bearing motors should be in the center of its mechanical float.

NOTE: Pr

oper alignment is essential for correct pump opera-

tion. This should be performed after base plate has been
properly set and grout has dried thoroughly according to
instructions. Final alignment should be made by shimming
driver only. Alignment should be made at operating
temperatures.

FIGURE 4 – FOUNDA

TION

FIGURE 5 – SETTING BASE PLATE AND GROUTING

WARNING: Unexpected Start-up Hazard

Disconnect and lock out power befor

e servicing.

Failure to follow these instructions could result in serious
personal injury or death and property damage.

PIPE

SLEEVE

FOUNDATION

BOLT

BUILT-UP

CONCRETE FOUNDATION

GROUT ONLY TO

TOP OF BASE RAIL.

PUMP

BASE RAIL

APPROX.

1" GAP

CONCRETE

FOUNDATION

LEVELING OF PUMP BASE

ON CONCRETE FOUNDATION.

GROUT

WASHER

ALLOW 1" FOR SHIMS.

PLACE ON BOTH SIDES

OF ANCHOR BOLTS.

NOTE:

TO KEEP SHIMS IN

PLACE ALLOW GROUT

TO FLOW AROUND

HOLD DOWN LUGS.

(OPTIONAL)

6