Check

Explanation/comment

Checked

Check that the pipeline has isolation valves around

the pump and has a drain valve in the suction pipe.

Use PTFE tape sealer or a high quality thread sealant

when you install the suction and discharge

connections to a threaded pump housing.

On an open system, check that the end of the suction

pipe is at least 3 ft. below the surface of the water in

the suction well.

This prevents air from being drawn into the

pump. Avoid air pockets in the suction line and

make sure that each section of the suction pipe

is air tight.

Check that new flange gaskets are installed between

the flanges of the pump body end suction and

discharge pipes. make sure that these gaskets are

clean and grease-free.

Suitable fasteners for this connection are

supplied in the Xylem fastener pack. Apply a

torque of 8 to 11 ft. lbs (11 to 15 Nm) to each of

the flange bolts. Both the suction and

discharge flanges must be torqued to the same

level.

Typical installation

1

2

3

4

5

6

7

8

9

10

11

1.

Locate the compression tank on the suction side of the pump

2.

Rolairtrol air separator

3.

System supply

4.

Circuit setter

5.

Triple duty valve

6.

Series 90 pump

7.

Suction diffuser

8.

Isolation valve

9.

Pipe from boiler chiller or converter

10. Cold water supply

11. Reducing valve