Pre-assembly inspections, Replacement guidelines, Reassembly – Xylem P81547D Series 90 In-Line Centrifugal Pump User Manual

Page 22: Reassemble the seal assembly

Advertising
background image

NOTICE:
These seal assemblies consist of a stationary seal insert assembly and a rotating seal
assembly. Each of these components must be replaced when you replace the
mechanical seal. Never replace individual components separately.

5. Remove the ring collar and remaining seal components from the shaft.
6. Use a clean, lint free rag in order to remove any debris that has accumulated in the seal

recess.

Pre-assembly inspections

Guidelines

Before you assemble the pump parts, make sure you follow these guidelines:

• Inspect the pump parts according to the information in these pre-assembly topics

before you reassemble your pump. Replace any part that does not meet the required
criteria.

• Make sure that the parts are clean. Clean the pump parts in solvent in order to remove

oil, grease, and dirt.

NOTICE: Protect machined surfaces while you clean the parts. Failure to do so may
result in equipment damage.

Replacement guidelines

Impeller replacement

This table shows the criteria for replacing the impeller:

Impeller parts

When to replace

Impeller vanes

• When grooved deeper than 1/16 in. (1.6 mm), or
• When worn evenly more than 1/32 in. (0.8 mm)

Vane edges

When you see cracks, pitting, or corrosion damage

Gaskets, O-rings, and seats replacement

• Replace all gaskets and O-rings at each overhaul and disassembly.
• Inspect the seats. They must be smooth and free of physical defects.
• Replace parts if the seats are defective.

Reassembly

Reassemble the seal assembly

WARNING:
After you disassemble a gasket joint, always use a new gasket upon reassembly. Never
reuse old gaskets. Failure to follow these instructions can result in serious personal injury,
death, and/or property damage.

1. Install the seal insert:

Maintenance

Series 90 Installation, Operation, and Maintenance Manual

21