INSTALLATION
Motor Cable Grounding Test
Do not connect the pump control cable
to the control box or incoming voltage
before verifying the pump ground;
otherwise, personnel will be exposed to
serious injury or death.
Using a volt-ohm meter, connect one lead to the
motor cable green/yellow ground lead. Connect
the other lead to an uninsulated point on the pump
body. The test circuit should close.
If the test circuit does not close, there is a defect in
the cable or motor which must be corrected.
Control Box Connections
This pump is shipped completely wired for the volt-
age shown on the nameplate, and is ready for op-
eration through an approved control box.
Ground and wire the control box in accordance
with the instructions accompanying it.
NOTE
For reference, internal motor wiring connections
are shown in the Maintenance and Repair manual.
- SM4G1-X30 575/3 1002211 thru 1241783 SM4J1-X60 460/3 1004954 thru 1241784 SM4C1-X10 460/3 1136140 and up SM4C1-X10 575/3 1136140 and up SM4C18-X10 460/3 1136140 and up SM4C18-X10 575/3 1136140 and up SM4C65-X10 460/3 915775 and up SM4C65-X10 575/3 915775 and up SM4D1-X10 460/3 1094445 and up SM4D1-X10 575/3 1094445 and up SM4D65-X10 575/3 915775 and up SM4D65-X10 460/3 915775 and up