3 alarm connections, 4 grounding, 1 frame ground – Alpha Technologies DCP03 300A User Manual

Page 18: Alarm connections, Grounding

Advertising
background image

020-702-C0 Rev C WC

Page 12 of 16

5.3 Alarm Connections

Terminal blocks can accommodate wire sizes #16 to #26 AWG (1.5 to 0.14mm²).
Route via wire-ways and use existing cable clamps to secure to existing (factory) wire harness along with

customer run signal wires. Ensure signal wires are routed along hinge point of front door so door opening and

closing won’t require excess wire slack. Refer to Figure 10 for wire routing example.
Terminal block connections for the internal alarm card, CXCI I/O, or CXCM2 I/O should be routed along the left

side of the DCP03 (looking at unit from front). Connections to the 4R/8D should be routed along the right hand

side of the DCP03. Refer to the customer connections (020-702-08) drawing at the rear of this manual for details

on terminal block assignments.

Figure 10–DCP03 wire routing example (List 74 and 79 shown)

(Photo is for reference only – subject to installation requirements)

5.4 Grounding

The isolated distribution center battery return bus (BRB) should be connected to the building master ground bus

(MGB) or floor ground bus (FGB) in a larger building. This acts as a system reference and as a low impedance

path to ground for surges, transients, noise, etc. The MGB or FGB should have a direct low impedance path to

the building grounding system. The cable from the distribution center to the MGB or FGB should be sized to

provide sufficient ampacity to clear the largest fuse or breaker on the distribution center, excluding the battery

protection fuse or circuit breaker. This is the minimum requirement; other factors including length of cable and

special grounding requirements of the load should also be factored in. The insulated cable should be equipped

with two-hole crimp type lugs and should not have any tight bends or kinks.
The distribution center frame must also be connected to the MGB or FGB. This is done for personnel safety and

to meet many Telco grounding requirements. Each bay should have its own frame ground connection. The

minimum recommended wire size is #2 AWG (35mm²).

5.4.1 Frame Ground

The DCP03 is grounded utilizing screws/bonding washers to the relay rack then to the main grounding bus using

#2 AWG (35mm²) insulated cable.

System Internal and

CXCI wire routing

Cable clamp

4R/8D ADIO or 8R/8D 8DIO wire routing

4R/8D ADIO or 8R/8D 8DIO

CAN ports