3.2. STANDARD INSTALLATION STEPS
The
Aegis Coil Scale Platform
standard installation consists of the following
steps.
A. Unpack scale, and check off all components.
B.
Prepare
tools, materials and documentation.
C. Select site location.
D. Foundation check, layout, and base plate setting.
E. Set up deck.
F. Set deck on load cells.
G. Level platform.
H. Install and wire instrument to platform.
I. Adjust and calibrate scale according to appropriate indicator service
manual.
J. Install coil cradle (if applicable).
3.2.1. Standard Components
The
Aegis Coil Scale Platform
is shipped with these standard components:
• The Weighbridge Platform
• Load Cells
• Load Cell Base Plates
• Side Checking Assemblies
• Mounting Hardware
• Analog Junction Box