HTP MC120 User Manual

Page 49

Advertising
background image

49

LP-171 Rev. 4.10.14


*NOTE: Installer must supply trap to meet local code requirements.

It is very important that you are connected to the type of gas noted on
the rating plate. “LP” for liquefied petroleum, propane gas, or “NAT” for
natural or city gas. You must not do a gas conversion without an
approved gas conversion kit. Prior to turning the gas on, all gas
connections must be approved by the local gas supplier or utility, in
addition to the governing authority.

A gas conversion kit comes with the heater. Follow the included
instructions VERY carefully. Failure to follow gas conversion
instructions could result in property damage, serious injury, or death.

Do not remove the adaptor in Figure 28! It is mandatory that this fitting is used
for connection to a field fabricated drip leg per the National Fuel Gas Code. You
must ensure that the entire gas line to the connection at the heater is no smaller
than ¾".

Do not attempt to support the weight of gas piping with the heater or its accessories. The gas valve and blower will not support the
weight of the piping. Failure to follow this warning could result in substantial property damage, severe personal injury, or death.

Once all inspections have been performed, the piping must be leak tested. If the leak test requirement is a higher test pressure than the
maximum gas inlet pressure, you must isolate the heater from the gas line to continue leak testing. To do this, you must turn off the
factory and field-installed gas cocks. This will minimize the possibility of damaging the gas valve. Failure to do so may damage the gas
valve. In the event the gas valve is exposed to a pressure greater than ½ PSI, 14" water column, the gas valve must be replaced. Never
use an open flame (match, lighter, etc.) to check gas connections.

Refer to the table below to size the supply piping to minimize pressure drop between meter or regulator and unit.

Maximum capacity of pipe in cubic feet of gas per hour for gas pressures of .5 psi or less and a pressure drop of .3 inch water column.

Nominal Iron

Pipe Size

(Inches)

Internal

Diameter

(Inches)

Length of Pipe (Feet)

BTU’s

Per Hour

x

1,000

10

20

30

40

50

60

70

80

90

100

125

150

175

200

¾

.824

278

190

152

130

115

105

96

90

84

79

72

64

59

55

1

1.049

520

350

285

245

215

195

180

170

160

150

130

120

110

100

1 ¼

1.380

1,050

730

590

500

440

400

370

350

320

305

275

250

225

210

1 ½

1.610

1,600

1,100

890

760

670

610

560

530

490

460

410

380

350

320

Table 8

It is recommended that a soapy solution be used to detect leaks. Bubbles
will appear on the pipe to indicate a leak is present. The gas piping must
be sized for proper flow and length of pipe to avoid excessive pressure
drop. Both the gas meter and the gas regulator must be properly sized for
the total gas load. If you experience a pressure drop greater than 1" WC,
the meter, regulator or gas line is undersized or in need of service. You
can attach a manometer to the incoming gas drip leg by removing the cap.
The gas pressure must remain between 3.5" WC and 14" WC during
stand-by (static) mode and while in operating (dynamic) mode at full
output.

If an in-line regulator is used, it must be a minimum of 10 feet from
the heater. It is very important that the gas line is properly purged by
the gas supplier or utility. Failure to properly purge the lines or
improper line sizing will result in ignition failure.
This problem is
especially noticeable in NEW LP installations and also in empty tank
situations. This can also occur when a utility company shuts off service to
an area to provide maintenance to their lines. The gas valve must not be
replaced with a conventional gas valve under any circumstances. As an
additional safety feature, the gas valve in this heater has a flanged

Figure 27

– LP-171-BB

Advertising
This manual is related to the following products: