Program examples, Tunnel building – Hired-Hand System 1000 Power Curtain Eight Stage Controller User Manual
Page 29

System 1000™ Power Curtain™ Controller
26
B.
End Cycle
C.
Art Light Relay #
8.
OSC High Mode
A.
OSC High Limit
B.
OSC Differential
C.
OSC Signal
D.
OSC Signal Relay #
9.
Fans Neg to Stir
10. View Records
A.
Sensor 1-4 low and high
B.
Sensor 1-4 Avg from Target
C.
Stages 1-8 Runtime
D.
Reset Records
11. System Clock
12. Calibrate Sensors
A.
Sensor #
B.
New Temperature
13. Run Adjustment
14. Initial Drop
15. Degrees Above Target Before Machine Operates
16. Set Ratios
17. Timer Period
18. Setup Timers
A.
Number of Timers
B.
Timer Mode
19. Save Level
A.
Level #
B.
This erases old level 1 Continue?
20. Restore Level
A.
Level #
B.
This changes the setup, Continue?
21. Sensors Display
22. Stage Temperature Display
23. Manually Set Speed
A.
Run Number
B.
Change Again
17. Program Examples
17.1. Tunnel Building
For this example we have a Tunnel Building with 9 Fans, 4 Heaters, and Foggers. For this setup,
we will not use OSC High, or Artificial lighting, as to make full use of the eight stages.
(Remember that each of these use one stage). We will use Expanded Timers.