Installation next to tanks containing one liquid and foam
• The top process connection of the bypass chamber must be above the maximum level of
liquid.
• The bottom process connection of the bypass chamber must be below the lowest measured
level of liquid.
Installation next to tanks containing more than one liquid
• The top process connection of the bypass chamber must be above the maximum level of
liquid.
• The bottom process connection of the bypass chamber must be below the lowest measured
level of liquid.
• Additional process connections are necessary for the liquids to circulate freely along the
length of the bypass chamber. These additional process connections must be separated by a
distance equal to or less than the minimum level of the bottom liquid.
Figure 3-10: Installation recommendations for bypass chambers that contain more than one liquid
1 Bypass chamber
2 Distance between connections ≤ the minimum level of the bottom liquid.
3 Additional process connection
.book Page 23 Thursday, September 3, 2009 2:53 PM