2 installing the spv controls danger – Sterlco SPV Remote Proportioning Devices User Manual

Page 13

Advertising
background image

Remote Proportioning Valve

Chapter 3: Installation

13 of 28

3-2 Installing the SPV Controls

DANGER!

Disconnect and lock out power before working on equipment. Do not
reconnect electric power until the installation is complete, the work has
been checked, and all tools are removed, and all safety devices are
activated. All electrical work must conform to all codes in effect at the
installation site.

Installing the SPV-A Autoload Knob Box Control

If your SPV has the SPV-A control package, use the following procedure to install it:

1. Disconnect and lock out power to the Autoloader Hopper Loader.

2. Wire the SPV Material A and B solenoids to the Autoloader Hopper Loader control

box using 16AWG wire. See Figure 3.

3. Remove Jumper W3 installed between Terminals 13 and 14 on Terminal Block TB1

in the Autoloader Hopper Loader control box.

Note: The knob box control will not function properly unless you remove this jumper.

4. Toggle the power switch on the Autoload Hopper Loader to the ON position. This

switch must be ON to use the Knob Box Control as a remote ON/OFF switch.

5. Plug the white logic plug connected to the SPV knob box into the receptacle marked

J2 on the left side of the Autoloader control enclosure. See Figure 4 on page 14.

6. Re-connect power.

Figure 3: SPV-A to Autoloader Wiring Diagram