Installation, 2 installing the conduit connection kit – APC BC300 User Manual
Page 7

Installation
990-1400A
Installation Guide APC BC300 Series 60kW 208/480V UPS
7
3.1.1 UPS Footprint (measurements in inches & mm)
Figure 1 - Footprint
3.2
Installing the Conduit Connection Kit
Insulated and other tools required
•
13 mm ratchet or wrench
•
T20 torx screwdriver
36.00 (914)
Minimum Service
Clearance
39.4
(1000)
31.7
(804)
59.1
(1500)
A
A
Front View
Side View
36.00 (914)
Recommended
Cooling
Clearance
31.7
(804)
Section A-A
View From Inside Cabinet, Looking Down
Conduit
Connection
Box
Cable Entry
(Rear)
(Front)
17.9
(455)
17.9
(455)
39.4
(1000)
19.8
(504)
27.9
(708)
31.7
(804)
Notes:
1. All dimensions are in inches (millimeters).
2. Minimum cooling and service clearance 36.00 (914).
3. Conduit entry is bottom of unit.
4. Unit weight = 2214lbs (1005kg)
5. Installation must comply with all applicable national and local codes