INSTALLATION INSTRUCTIONS

for Wood Bay & Bow Windows with Nailing Fin or Exterior Trim (JII032)

3

Note!

This section

applies to installations
into a masonry wall
only. For installations
into a stud-framed
wall, begin with
section 4, “PREPARE
STUD-FRAMED
WALL.”
1. Seal any joint larger

than 1/16" in the
buck and between
the buck and the
concrete/masonry
with sealant.

INSPECT ROUGH OPENING

2

• Verify the width

and height of the
window are each
1/2" - 5/8" smaller
than the rough
opening width and
height.

A

B

D

C

E

• Verify the rough opening is square. The (A) and (B) measurements

above should be the same. Maximum allowable deviation from square
for windows over 20 sq. ft. is 1/4" and for windows under 20 sq. ft.
is 1/8".

• Verify the rough opening is level and plumb (C) and (D). The

maximum allowable deviation is 1/8".

• The rough opening sill must not be crowned or sagged (D). A 5

degree

sloped sill is recommended.

• Verify the exterior face of the rough opening is a single plane (E) with

less than 1/8" twist from corner to corner.

• Verify the rough opening is structurally sound.
• Correct any deviations before installing the window.

PREPARE BUCK

3

2. Cover the buck and the surrounding concrete/masonry at the head

and jambs with liquid applied flashing as shown.

3. If installing into a four-sided buck: Seal the sill in a similar manner.

Note!

Shims must be 1/4" shorter than the depth of the window sill,

should level the rough opening sill and be no more than 1/4" thick.
4. Shim the sill 4" from each corner, at 8" intervals, and underneath

mull joints on both sides with non water-degradable or compressible
shims. Secure shims with sealant. SKIP to section 5, “PREPARE
WINDOW.”

PREPARE STUD-FRAMED WALL

4

FOR RETROFIT INSTALLATIONS

After removing the old window, remove sufficient siding to expose
enough intact building wrap to properly seal the window to the
opening. If damaged, apply new building wrap in shiplap manner.
Verify the rough opening framing is structurally sound. Continue with
the instructions.

PREPARE BUILDING WRAP

Note!

Check with

the building wrap
manufacturer to verify
the following steps
will not void their
product warranty.
Follow manufacturers'
instructions.
1. Trim building wrap

flush with the
rough opening.

2. At the head, cut

building wrap at
45° and tape up as
shown.

3. Trim the sides sufficiently to allow the nailing fin to be mounted

against the sheathing.

45°

Sealant

joints

Liquid

applied

flashing