5

1. Fold the head board piece

lengthwise into “L” shape.

Center and apply one leg

to head board and the

other to the wall above the

rough opening header. Cut

the corners to allow the

flashing to lay flat against

the wall.

2. Starting 2" above the

header, apply the side

pieces and overlap the

drain mat on the sill as

shown.

3. Center and apply the

header piece above the

header, overlapping the

side pieces as shown.

4. Press the flashing down

with a J-roller, being

careful to remove any gaps

or bubbles beneath self-

adhesive flashing (remove

and replace if necessary).

Cut four pieces of self-adhesive flashing as follows:

• One head board piece 6" longer than the head board
• One header piece 12" longer than the header
• Two side pieces 7" longer than each side

SPRAY ADHESIVE/PRIMER

Apply spray adhesive/primer
as instructed to nailing fin,
sheathing and building wrap
at the sides and head as
shown.

APPLY THE SELF-ADHESIVE FLASHING

Note!

Keep the edge of the self-adhesive flashing as close to the

window frame as possible and apply over the nail fin.

FLASH WINDOW - WINDOWS WITH A NAILING FIN INSTALLED INTO STUD-FRAMING ONLY

6

Sp

ra

y

Ad

he

siv

e

6"

Fold

down

Cut

2"

6"

6"

2"

1. If the window has a pre-

installed cable support

system, follow the

instructions provided by

the manufacturer.

2. If the cable support system

is not used, build seat

board bracing to support

at least 750 lbs. of total

weight (window plus

window contents). Primary

support should be provided

under the mull joints of the

unit.

3. Remove temporary support

after full support is

installed.

4. Release the building wrap

from above the header

(previously taped up)

and overlap the header

flashing. Seal the ends with

self-adhesive flashing or building wrap tape.

5. Seal all four corners of the window with a 1/4" bead of sealant. Tool

into a fillet shape.

6. The head and seat boards should be protected and insulated with a

structure designed and built as required by local code.

COMPLETE INSTALLATION

7

Bracing Under the Mull Joints

Seal corners

Please visit www.jeld-wen.com for warranty and care and maintenance information.

Thank you for choosing

7. Create a continuous air seal

on the interior between

the rough opening and the

window frame with low

expansion polyurethane

foam or backer rod and

sealant. On the sill, the

foam or sealant must

create this air seal by

integrating the back of the

drain mat with the window

frame and the rough

opening.

AFTER INSTALLATION

1. Adjust window for best operation.
2. Install exterior wall surface within 30 days of window installation.
3. Maintain gap of 3/8" between window frame and final exterior wall

surface (siding, stucco, etc.).

4. Remove protective film from cladding (if present) immediately after

installation; remove from glass within one year.

5. Protect recently installed units from damage from plaster, paint, etc.

by covering the unit with plastic.

6. Finish all exposed wood surfaces immediately following installation.

(05/14)

©2014 JELD-WEN, inc.; This publication and its contents are owned by JELD-WEN, inc. and are protected under the U.S. Copyright Act and other intellectual property laws. All trademarks, service marks,
logos and the like (whether registered or unregistered) are owned or controlled by JELD-WEN, inc. or others. Unauthorized use or duplication of JELD-WEN intellectual property is prohibited.

JELD-WEN reserves the right to change product specifications without notice. Please check our website, jeld-wen.com, for current information.

Framing

Shim

Back of

flashing

Continuous

air seal

Advertising